Add Material Costs
Material can be added to a work order.
- Click the work order you want to add material to.
- Click Costs, then click Edit in the top-right corner. If you are already in edit mode, you don't need to click Edit.
- Click Add in the Material section.
- In the Add Material panel, click Crew to select a crew from the panel that opens.
- Click Material to select one or more materials you want to add, then click Save.
- Click Account to select an account from the panel that opens.
- Click the Units field and enter the quantity of the material that is needed.
- In the Date section, click the calendar icon to select the date, then click the clock icon to select the start time.
- Click the Entity field and select the desired entity, then click Save.
- Click Save at the bottom of the panel.
- Click Save in the top-right corner to save material to the work order.
The added material appears on the work order.