Add Material Costs

Material can be added to a work order.

  1. Click the work order you want to add material to.
  2. Click Costs, then click Edit in the top-right corner. If you are already in edit mode, you don't need to click Edit.

  1. Click Add in the Material section.

  1. In the Add Material panel, click Crew to select a crew from the panel that opens.
  2. Click Material to select one or more materials you want to add, then click Save.
  3. Click Account to select an account from the panel that opens.
  4. Click the Units field and enter the quantity of the material that is needed.
  5. In the Date section, click the calendar icon to select the date, then click the clock icon to select the start time.
  6. Click the Entity field and select the desired entity, then click Save.
  7. Click Save at the bottom of the panel.

  1. Click Save in the top-right corner to save material to the work order.

The added material appears on the work order.